Tray Rack Installation Timeline: A Guide to Planning from Design to Acceptance

Keywords:

Publish Time:

2025-10-29

 

 

In today's modern warehousing and logistics systems, pallet racking serves as the core storage equipment, and its efficiency and stability directly impact a company's operational effectiveness. Many enterprises, when planning their racking systems, often lack a clear understanding of the installation timeline, leading to project delays or unnecessary resource waste. This article will provide a detailed breakdown—from a professional perspective—of the complete timeline for pallet racking, from design to acceptance, helping you manage your project schedule more effectively and scientifically.

 

I. Preliminary Preparation Phase (1–3 business days) – Laying the Foundation for Efficiency
✅ Key actions: Requirement confirmation + on-site survey
This is the starting point that will determine whether all subsequent phases can proceed smoothly. Our engineers will have an in-depth discussion with the client to clarify the following key information:
▪️ Warehouse dimensions, load-bearing requirements, cargo types, and turnover frequency
▪️ Special functional requirements (such as anti-slip layers, corner protection devices, and预留 interfaces for automation upgrades)
▪️ Layout of fire escape routes, lighting systems, and other supporting facilities
Tip: If the warehouse has issues such as uneven flooring or obstructed columns, solutions should be planned in advance—otherwise, it may lead to rework and delays.

Simultaneous Execution: 3D Modeling Rehearsal
By constructing a 1:1 scale model using CAD software, we simulate shelf arrangement plans to visually verify the efficiency of space utilization and the rationality of workflow routes. Optimization points identified during this phase can help save time on later adjustments.

 

 

II. Deepen Design and Solution Confirmation (5–7 business days) – Customized Solutions
Technology Breakthrough Phase: Structural Mechanics Calculation + Material Selection & Matching
Based on load parameters (static/dynamic bearing capacity), seismic intensity data, and other relevant information, accurately calculate the column section dimensions and beam deflection values, and select the appropriate steel grade (Q235B/Q345B). For heavy-duty shelving systems, a finite element analysis must also be conducted to simulate extreme operating conditions.

Deliverable: A formal proposal document including the following content
✔️ Floor Plan & Elevation Section
✔️ Load Distribution Table and Safety Factor Explanation
✔️ Accessory List (including main frame, secondary frame, shelf boards, back sealing mesh, etc.)
✔️ Initial Draft of Construction Progress Gantt Chart
Experience sharing: It's recommended to allow 12 days of buffer time for the client's internal approval process.

 

III. Production and Manufacturing Phase (10–15 working days) – Precision manufacturing ensures quality
Highlights of the production process:
▶︎ Fully automatic cold-forming production line processes columns and beams, with tolerances controlled within ±0.5mm.
▶︎ Surface treatment employs acid pickling and phosphating combined with electrostatic powder coating, enhancing rust resistance by more than threefold.
▶︎ Each batch of raw materials is accompanied by a material report, and critical welds undergo X-ray inspection.
Time-sensitive management: Set up production milestone reminders, update the progress dashboard daily, and immediately activate the emergency response plan in case of unexpected situations.

Logistics Collaboration:
After being packaged, finished products are categorized and labeled by region, accompanied by a Packing List and an Installation Manual in each vehicle. Throughout the transportation process, they are continuously tracked via GPS positioning.

 

IV. On-site Installation and Commissioning (35 working days) — Standardized Procedures Ensure Safety
Construction Team Configuration:
The project manager, certified welder, forklift operator, and quality inspector form a dedicated team to strictly adhere to GB/T 4996-2010, "General Technical Specifications for Interlocking Steel Shelving."

Standard Procedure:
| Steps | Duration | Quality Control Highlights |
| Foundation Treatment | 0.5 day | Concrete curing strength ≥ C25, horizontal error < 2 mm/m |
| Column Assembly | Day 1 | Verticality Deviation ≤ H/500, Anchor Bolt Torque Meets Specifications |
| Beam Installation | Day 1 | Ensure uniform spacing between layers and that the end safety pins are fully engaged |
| Safety Protection | 0.5 Day | Install anti-collision bollards, warning signs, and post load-bearing labels |
| Collaboration Test | 0.5 Day | Simulate fully loaded stacking, checking deformation levels and audio-visual alarm functionality |

Emergency Mechanism: Equipped with a backup component kit, enabling immediate cutting and modification for non-standard sizes, thereby minimizing downtime due to material shortages.

 

V. Acceptance and Delivery Phase (12 Business Days) – Multi-Dimensional Quality Control
Three-level acceptance system:
① Self-inspection: The construction unit shall verify each item according to the "Unified Standard for Quality Acceptance of Building Engineering Construction."
② Special Inspection: A third-party testing agency issues the "Shelf Static Load Test Report" and the "Coating Thickness Inspection Report."
③ Final Verification: The customer, together with the warehousing department, conducts a hands-on practice session, focusing on verifying:
✓ Forklift access and retrieval efficiency
✓ Overall shelf stability (apply 1.2 times the rated load and observe deformation)
✓ Attachment Integrity (shoe guards, label tags, etc.)

Deliver the document package:
In addition to the standard instruction manual, we also provide an extra "Maintenance and Care Manual" and a "Troubleshooting Guide for Common Issues," along with establishing a dedicated after-sales service file.


6. Core Variable Factors Influencing the Cycle
| Factors | Typical Impact Magnitude | Mitigation Strategies |
| Warehouse Complexity | ±20% | Engage in civil engineering design early to预留 expansion joints |
| Customization Level | +30% → 50% | Modular design reduces non-standard rates |
| Seasonal Factors | Rainy Season Extended by 23 Days | Schedule Construction Outside the Plum Rain Season |
| Cross-departmental Coordination | ±15% | Designate a dedicated point of contact and hold weekly progress meetings |


Professionalism builds efficiency, while attention to detail ensures safety.

A complete pallet racking project is not only the implementation of an industrial product but also a true test of supply chain collaboration capabilities. With two decades of industry experience, Guangdong Xiada Racking Company has established a comprehensive management system that covers design optimization, intelligent manufacturing, and lean construction processes. We promise: while maintaining top-notch quality, we’ll leverage meticulous project management to reduce the average installation timeline to industry-leading levels. If you’re looking for a personalized schedule plan, feel free to give us a call—we’ll tailor the most efficient warehousing solution specifically for your needs!

 